Latest News

Fun at the Farm!

One day we (the kids) built a den. It was so much fun! We made the den camouflaged (by putting moss from the other side of what’s going to be Leo’s house in front of  the swing in the courtyard onto both of our rooves, one blue tarpaulin one black) and used real nails. We used pallets for the walls and we made a treasury. Once, we made a fire by clearing out the prickly brambles from a stone pit. Also, we nailed thin polystyrene to stop the wind from coming in. In the den, there are three rooms: One is a room with a little stone opening and a table and two benches that we nailed together. We made the benches with a thin piece of wood and two small cuboids, which we nailed to each side. the next room is a treasury of slag from iron furnaces which we put on some shelves that we made by hammering nails into pieces of wood onto the pallets. The treasury also has a bench but this one isn’t as sturdy as the two in the first room. We have built the third room much more recently than the other two so we haven’t really put anything into it yet but we hopefully will very soon. We had so much fun that day because we knew that it will be there for a long time and we can always go and play in it whenever we want.

By Raymond (8) and Lydia (7)

Since then we had a super hot weekend with the gym mat being converted into a water slide. More recently the Connors came for a working weekend and the fun continued! Working weekends are the second weekend in every month. All help appreciated! Polly

Photo 12-03-2017, 07 38 18Photo 12-03-2017, 07 40 54Photo 12-03-2017, 07 41 24Photo 23-04-2017, 16 11 13Photo 24-04-2017, 10 40 15Photo 24-04-2017, 13 12 33Photo 24-04-2017, 13 13 34Photo 24-04-2017, 13 14 20Photo 24-04-2017, 13 15 07Photo 24-04-2017, 13 16 41WP_20170408_12_20_23_Pro

Pumping the Slab!

The third  area of floor that  needed a concrete slab proved inaccessible for direct pour-in so we hired an intermediary in the form of a large pump on the back of a lorry.

IMG_0307

IMG_0306

At one time there were six men involved – only Scott seemed prepared to take a headlong plunge into the ready mix as he waded about on an uneven surface with the concrete lapping about near the top of his wellies. I thought the others were waiting to rush to his rescue should he falter, but when asked what they would do if he fell in, they replied, without hesitation, – “Laugh!”

IMG-20170329-WA0001

 

The process got more technical towards the end!

IMG_0314

A Fine Job and no accidents!

 

Sowing the seeds of summer

The winter gardener reviews the successes and failures of the previous seasons’ crops, tidies the polytunnel, gets excited about seed catalogues and draws up plans for the crop rotation for the new growing year. Growing plans below from left to right – the outside beds, the polytunnel bed, the long outside bed. The brassicas (blue) like to follow where the legumes (green) were last year to take up the nitrogen left in the soil and the roots (orange) fit in the areas left. There are some odd vegetables like artichokes and sweetcorn which don’t belong to a category and just get put wherever there’s space.

Beds2017  Tunnel 2017

I particularly enjoy choosing the seeds we’ll order with Sheila. When reading about the properties of different varieties you can believe the promises of ‘prize-winning quality, rust resistance, and sweet tasting roots’ and imagine a year of perfect vegetable success untroubled by aphids and slugs and powdery mildew. The planning phase feels so hopeful.

WP_20170220_14_40_10_Pro   wp_20170316_15_11_40_pro.jpg

Above is the beginnings of our tomato jungle (and some pak choi seedlings) that occupies half the polytunnel each year. This season a cherry variety called Red Pear will be our main crop, with smaller numbers of Harbinger, Black Opal and a yellow variety called Sungold. I brought in the seed modules to the Byre and I think the underfloor heating provided them with lovely conditions for germination, forget electric propagators!

WP_20170312_11_04_04_Pro

The carrots, broad beans and peas which were sown in the autumn have been on hold over winter in the tunnel and are now starting to grow in earnest again. We’ve been eating Russian and curly kale, lettuce and red cabbage throughout winter and the minimal Brussel sprout crop managed to provide enough for  group dinner on Christmas day.

WP_20170312_11_03_25_Pro

Above shows the outdoor beds in their winter covering, sparse vegetation and carpet to reduce the weeding come spring. The blackcurrants and redcurrants in the foreground have been pruned to a ‘goblet shape’ by removing low and centre branches to encourage fruit. This fruit border is full of alliums, daffodils, tulips and crocuses yet to flower and mark the start of spring . One of gardening aims is to grow more flowers this year, particularly varieties suitable for a semi-wild garden and cutting, as we all enjoy having flowers in our homes. There will be sweet peas, delphiniums, cosmos, larkspur, cornflowers, hollyhocks, sunflowers, foxgloves and poppies to name a few.

The orchard is growing happily, now with crocuses flowering around the base of the trees. Sheila has taken to regularly inspecting the buds just beginning to open on the fruit trees and has developed a theory about the fat buds being the fruit producing ones and the narrow buds producing only leaves – we’ll see if she’s right come summer!

WP_20170312_11_00_50_Pro

I realise this is a vegetable heavy blog and many readers might not be into gardening. Whilst I did grow up in a family that grew their own veg I hadn’t done much myself before we bought the farm. I’ve discovered it’s not so complicated, you do what is says on the back of the packet and if it goes well you do the same the next year, if it doesn’t you try something different till you discover what works in your soil and the micro climate of your garden. So hopefully this will inspire  a few of you to get some seeds, a pot and a bit of compost and grow something edible at home.

Hitting the ground…

Now inside the barn, we started to plan the removal of the existing timber floor that was not structurally sound. taking up the boards was simple enough with a scaffolding pole for leverage. The beams, however, were another matter! It required 4 people, 2 acrowprops, 1 mini-digger, 1 chainsaw and series of the ropes. By propping-up the beams and then sawing through them, then lowering the loose end down to the ground with the arm of the digger, we managed to complete the task. It was another example of problem solving, teamwork and brutally delicate work!

DSC_1285DSC_1317

Once the beams were removed, we were able to deconstruct the internal stone wall, carefully taking the blocks (some up to 1m long and 220x300mm in section) down in the bucket of the dumper truck. Each cut block was set aside to be re-used at a later date.

DSC_1321

With the barn clear of obstacles, we set about digging out for the foundation strips and organising the ground floor levels. Before embarking on any excavations of the ground we arranged for our archaeologist to oversee the work, checking for clues as to the previous use of the buildings.

DSC_1343

Following the excavations we were able to create the 3 levels of the ground floor and cast the foundation strips. This meant substantial movement of earth around the ground area, which Paul made light work of!

DSC_1390

The new walls started to be erected just above the level of the floor, so that we could then go on to cast the floor slabs.

DSC_1765

The foul drainage pipework was also installed, with pea-gravel bed and connections formed through the hefty stone walls of the barn. After some shenanigans with pipe work for the district heating system (probably requires another blog to explain) we were ready to prepare the ground for the casting of the concrete slabs. After shifting more earth and compacting it to be a solid bed, 3 tonnes of sand was used to create the blinding (layer to stop any sharp stones tearing the damp proof membrane (dpm). Then we set about laying and taping the dpm, laying out the reinforcement mesh and resting it on the castles. With a willing team, this was achieved in half a day… ready for the concrete pouring!

DSC_1404

DSC_1773

This all took several months to complete, with over over 10 different builders involved!

 

 

From ridge to eaves

Following the completion of the new (reclaimed) roof covering it was time to move back inside the building as the winter weather set in. Having a water tight roof meant we could start insulating and and creating the internal roof finish.

DSC_1172

In order to make the building thermally efficient, we are incorporating 150mm of high performance insulation into the roof. Due to the existing construction this needed to be built up in 3 x 50mm layers, one between the rafters, the second as full sheets below the rafters and the third, incorporated into a new layer of studwork. The overlapping layers help ensure a good level of airtightness, which is a particular challenge in a building where each structural element is a different shape. This was a substantial task that our builders seemed to complete in a short time!

DSC_1109

Then it was the turn of the plasters to enter the fray and board out the roof, before applying the skim finish. It’s always a really exciting moment in the build, when you have some crisply plastered areas and it made the whole project seem substantially closer to completion (relatively speaking!).

DSC_1207

There was just time after this to apply a coat of paint to the roof. This seemed like a really odd thing to do, considering that the rest of the building was untouched! However, it made sense to do this while the internal scaffolding (or the ‘dance floor’, as Joe calls it) was still there.

DSC_1277

In order to keep maintain some way of accessing the roof space internally once the scaffolding was struck, we used some spare planks to fix between the trusses and strung a safety line between them. Whilst this was a practical move, it also created a safe high-level walkway that Greg could not help but investigate (when there was no work going on underneath) with the kids. Wearing climbing harnesses and helmets, the older children were able to walk between the trusses some 7m off the ground; a kind of architectural via ferrata!

DSC_1302

With the internal scaffolding removed, the full glory of the internal space was revealed! You could really see and feel the difference that the roof lights made. The top-lit space picked out the existing walls and some of the stones that projected out from the wall.

DSC_1289

With the roof now complete, it was back to terra firma for ground works!

Old and New Roof

Having removed some 50+ tonnes of stone from the roof, it was time to assess the 200 year old timber structure. Comprising 10 trusses (each numerically marked for their exact positioning) and 2 dragon tie joints at the hipped roof, the structure is beautifully crafted, but in need of some TLC.

dsc_0890

The timber structure had decayed in places with woodworm attack. We therefore needed to spray the entire structure with preservative, which was no mean feat!

dsc_0938

Although largely in good condition the roof required some repairs to trusses, purlins and rafters. Most repairs will be covered with insulation and plasterboard, but some of the ties within the trusses will be seen. We have deliberately left the new timber elements to act as a contrast to the old and show the ongoing evolution of the building.

unit-5-roof

In order to try and reduce the waves in the roof, the builders had to pack virtually every slate lath. The roof slates are reclaimed welsh slate which gives a nice contrast to the stone walls.

 

The creation of two apex rooflights proved a challenge, as they came as a kit of parts. However, this enabled our builders to customise the details to suit our project.

 

The reclaimed clay ridge tiles finish the roof, and they have just about gone on before the deluge of rain that we had last week. In general, we have been incredibly lucky with the weather and have had little rain or wind to contend with while the roof structure sat naked!

 

With this crucial job now complete, we can concentrate on working inside the building over the winter period! Now for the insulation!